[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-895125":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},895125,581,1,"单选题","《建设工程工程量清单计价规范》（GB50500—2013）规定,招标时用于合同约定调整因素出现时的工程材料价款调整的费用应计人（）中。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","分部分项综合单价",false,{"key":16,"text":17,"correct":18},"B","暂列金额",true,{"key":20,"text":21,"correct":14},"C","材料暂估价",{"key":23,"text":24,"correct":14},"D","总承包服务费","本题考核暂列金额包含的项目。清单计价规范中规定暂列金额是用于合同签订时尚未确定或者不可预见的所需材料、设备、服务的采购，施工中可能发生的工程变更、合同约定调整因素出现时工程索赔、现场签证确定等的费用。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]