[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-895124":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},895124,581,1,"单选题","采用工程量清单计价方式招标时，对工程量清单的完整性和准确性负责的是（）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","编制招标文件的招标代理人",false,{"key":16,"text":17,"correct":14},"B","编制清单的工程造价咨询人",{"key":19,"text":20,"correct":21},"C","发布招标文件的招标人",true,{"key":23,"text":24,"correct":14},"D","确定中标的投标人","工程量清单应由具有编制能力的招标人或受其委托具有相应资质的工程造价咨询人编制。采用工程量清单方式招标，工程量清单必须作为招标文件的组成部分，其准确性和完整性由招标人负责。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]