[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-895123":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},895123,581,1,"单选题","根据《建设工程工程量清单计价规范》（GB50500—013）的规定，在合同约定之外的或者因变更而产生的、工程量清单中没有的且难以事先商定价格的额外工作，应计列入（）之中。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","暂列金额",false,{"key":16,"text":17,"correct":14},"B","暂估价",{"key":19,"text":20,"correct":21},"C","计日工",true,{"key":23,"text":24,"correct":14},"D","措施项目费","计日工对完成零星工作所消耗的人工工时、材料数量、施工机械台班进行计量，并按照计日工表中填报的适用项目的单价进行计价支付。零星工作一般是指合同约定之外的或者因变更而产生的、工程量清单中没有相应项目的额外工作，尤其是那些难以事先商定价格的额外工作",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]