[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-895122":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},895122,581,1,"单选题","下列措施项目中,适合采用综合单价方式计价的是（）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","已完工程及设备保护",false,{"key":16,"text":17,"correct":14},"B","二次搬运费",{"key":19,"text":20,"correct":14},"C","安全文明施工",{"key":22,"text":23,"correct":24},"D","混凝土、钢筋混凝土模板",true,"本题考核清单措施项目计价的两种方法。能明确计算工程量的可釆用综合单价报价,混凝土、钢筋混凝土模板费用可计算工程量，适合采用综合单价计价。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]