[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-895118":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},895118,581,1,"单选题","分部分项工程量清单项目编码以五级编码设置，其中第四级编码为()。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","工程分类顺序码",false,{"key":16,"text":17,"correct":14},"B","专业工程顺序码",{"key":19,"text":20,"correct":14},"C","分部工程顺序码",{"key":22,"text":23,"correct":24},"D","分项工程项目名称顺序码",true,"分部分项工程量清单项目编码以五级编码设置，用十二位阿拉伯数字表示。一、二、三、四级编码为全国统一，即一至九位应按计价规范附录的规定设置；第五级编码应根据拟建工程的工程量清单项目名称设置。各级编码代表的含义分别为：第一级表示工程分类顺序码（分二位）；第二级表示专业工程顺序码（分二位）；第三级表示分部工程顺序码（分二位）；第四级表示分项工程项目名称顺序码（分三位）；第五级表示工程量清单项目名称顺序码（分三位）。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]