[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-895102":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},895102,581,1,"单选题","若清单计价规范中的项目名称有缺陷，则处理方法是()。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","招标人作补充，并与投标人协商后执行",false,{"key":16,"text":17,"correct":14},"B","投标人作补充，并与招标人协商后执行",{"key":19,"text":20,"correct":14},"C","投标人作补充，并报当地工程造价管理机构（省级）备案",{"key":22,"text":23,"correct":24},"D","招标人作补充，并报当地工程造价管理机构（省级）备案",true,"计价规范中的分项工程项目名称如有缺陷，招标人可作补充，并报当地工程造价管理机构（省级）备案。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]