[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-895097":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},895097,581,1,"单选题","措施项目清单编制中，下列适用于以“项”为单位计价的措施项目费是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","已完工程及设备保护费",true,{"key":16,"text":17,"correct":18},"B","超高施工增加费",false,{"key":20,"text":21,"correct":18},"C","大型机械设备进出场及安拆费",{"key":23,"text":24,"correct":18},"D","施工排水、降水费","本题考查的是措施项目清单的编制。有些措施项目则是可以计算工程量的项目，如脚手架工程，混凝土模板及支架（撑），垂直运输，超高施工增加，大型机械设备进出场及安拆，施工排水降水等。不能计算工程量的项目清单，以“项”为计量单位进行编制。采用排除法，可选A。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]