[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-895074":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},895074,581,1,"单选题","关于工程定额计价模式的说法，不正确的是（）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","编制建设工程造价的基本过程包括工程量计算和工程计价",false,{"key":16,"text":17,"correct":14},"B","定额的特点是具有相对稳定性",{"key":19,"text":20,"correct":21},"C","定额计价中不考虑不可预见费",true,{"key":23,"text":24,"correct":14},"D","定额在计价中起指导性作用","本题考核的知识点为工程定额的特点及工程定额计价模式的程序。工程定额的特点有：科学性、系统性、统一性、指导性、稳定性与时效性。工程定额的稳定性是相对的。我国在很长一段时间内采用单一的工程定额计价模式形成工程价格，即按预算定额规定的分部分项子目，逐项计算工程量。套用预算定额单价(或单位估价表)确定直接工程费，然后按规定的取费标准确定措施费、间接费、利润和税金，加上材料调差系数和适当的不可预见费，经汇总后即为工程预算或标底。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]