[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-895066":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},895066,581,1,"单选题","某建设项目工程费用为7200万元，工程建设其他费用为1800万元，基本预备费为400万元，项目前期年限1年，建设期3年，各年度完成投资计划额的比例分别为20%、40%与40%，年涨价率为6%，则该项目建设期第二年价差预备费为()万元。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","451.63",false,{"key":16,"text":17,"correct":14},"B","464.74",{"key":19,"text":20,"correct":14},"C","564.54",{"key":22,"text":23,"correct":24},"D","589.63",true,"考生应掌握价差预备费的计算公式，并且应注意价差预备费的计算基数为静态投资。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]