[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-895064":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},895064,581,1,"单选题","某建设项目在竣工验收时，为了鉴定一项隐蔽工程质量，进行了必要挖掘，则该项挖掘费用应计入()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","涨价预备费",false,{"key":16,"text":17,"correct":18},"B","基本预备费",true,{"key":20,"text":21,"correct":14},"C","间接费",{"key":23,"text":24,"correct":14},"D","其他间接费","基本预备费是指投资估算或工程概算阶段预留的，由于工程实施中不可预见的工程变更及洽商、一般自然灾害处理、地下障碍物处理、超规超限设备运输等而可能增加的费用，亦可称为工程建设不可预见费，",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]