[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-895048":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},895048,581,1,"单选题","某建设项目工程费用为2000 万元，工程建设其他费用为800 万元，已知基本预备费费率为10%,项目建设前期为1 年,建设期3 年，各年投资计划额为:第1 年20%,第2 年50%，第3 年30%。若年涨价率为5%，则该项目建设期间价差预备费为（）万元。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","418.61",true,{"key":16,"text":17,"correct":18},"B","334.30",false,{"key":20,"text":21,"correct":18},"C","323.4",{"key":23,"text":24,"correct":18},"D","505.01","建设项目静态投资=(2000+800)×(l+10%)=3080(万元） PF1=3080×20%×(1.051.5-1)=46.77(万元） PF2=3080×50%×(1.052.5-1)=199.78(万元） PF3=3080×30%×(1.053.5-1)=172.06(万元) PF=PF1+PF2+PF3=418.61(万元）",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]