[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-895036":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},895036,581,1,"单选题","某工业项目及其总装车间的各项费用如下表所示（单位：万元），则总装车间分摊的建设单位管理费为()万元。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","18.67",false,{"key":16,"text":17,"correct":14},"B","18.29",{"key":19,"text":20,"correct":14},"C","17.14",{"key":22,"text":23,"correct":24},"D","17.21",true,"建设单位管理费按照工程费用之和（包括设备工器具购置费和建筑安装工程费用）乘以建设单位管理费费率计算。建设单位管理费= 工程费用X建设单位管理费率建设单位管理费按建筑工程、安装工程、需安装设备价值总额等按比例分摊。(350+120+240)／(1500+600+1200)×80=17.21（万元）。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]