[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-895003":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},895003,581,1,"单选题","采用成本计算估价法计算非标准设备原价时，下列表述正确的是（）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","专用工具费＝（材料费＋加工费）×专用工具费率",false,{"key":16,"text":17,"correct":14},"B","加工费＝设备总重量×（1＋加工耗损系数）×设备每吨加工费",{"key":19,"text":20,"correct":14},"C","包装费的计算基数中不应包含废品损失费",{"key":22,"text":23,"correct":24},"D","利润的计算基数中不应包含外购配套件费",true,"本题考查是设备购置费的构成和计算。专用工具费=（材料费+加工费+辅助材料费）×专用工具费率；加工费=设备总重量（吨）×设备每吨加工费；包装费=（材料费+加工费+辅助材料费+专用工具费+废品损失费+外购配套件费）×包装费率；利润=（材料费+加工费+辅助材料费+专用工具费+废品损失费+包装费）×利润率。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]