[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-894996":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},894996,581,1,"单选题","下列费用中，属于建筑工程费用的是（）",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","建筑工程以及各种炉窑的砌筑工程和金属结构工程的费用",true,{"key":16,"text":17,"correct":18},"B","生产、动力、起重、运输、传动和医疗、实验等各种需要安装的机械设备的装配费用",false,{"key":20,"text":21,"correct":18},"C","对单台设备进行单机试运转的费用",{"key":23,"text":24,"correct":18},"D","对系统设备进行系统联动无负荷试运转工作的调试费","B、C、D 项费用属于安装工程费用的内容。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]