[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-894960":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},894960,581,1,"单选题","反映工程造价估算日期至工程竣工日期之前，工程各个主要组成部分的人工、材料和设备等未知价格增长部分的是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","直接建设成本",false,{"key":16,"text":17,"correct":18},"B","建设成本上升费",true,{"key":20,"text":21,"correct":14},"C","不可预见准备金",{"key":23,"text":24,"correct":14},"D","未明确项目准备金","本题考查的是建设成本上升费用的概念。通常，估算中使用的构成工资率、材料和设备价格基础的截止日期就是“估算日期”。必须对该日期或已知成本基础进行调整，建设成本上升费的目的就是补偿直至工程结束时的未知价格增长。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]