[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-894955":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},894955,581,1,"单选题","在国外的项目总建设成本中，未明确项目的准备金的目的是为了()。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","用来补偿估算的误差",false,{"key":16,"text":17,"correct":14},"B","支付工作范围以外可能增加的项目",{"key":19,"text":20,"correct":21},"C","支付那些估算时不可能明确的潜在项目",true,{"key":23,"text":24,"correct":14},"D","应付天灾、非正常经济情况及罢工等情况","未明确项目的准备金是用于支付那些估算时不可能明确的潜在项目。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]