[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-894953":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},894953,581,1,"单选题","对于非生产性建设项目，项目总投资不包括的内容为（）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","建设投资",false,{"key":16,"text":17,"correct":14},"B","建设期利息",{"key":19,"text":20,"correct":14},"C","预备费",{"key":22,"text":23,"correct":24},"D","铺底流动资金",true,"非生产性建设项目总投资包括建设投资和建设期利息两部分。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]