[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-894950":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},894950,581,1,"单选题","在世界银行工程造价的构成中，有一项费用有可能发生，有可能不发生,在正常建设条件下可能不动用，只是一种贮备。此项费用是（)。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","建设成本上升费用",false,{"key":16,"text":17,"correct":14},"B","项目间接建设成本",{"key":19,"text":20,"correct":14},"C","未明确项目准备金",{"key":22,"text":23,"correct":24},"D","不可预见准备金",true,"不可预见资金用于在估算达到了一定的完整性并符合技术标准的基础上，由于物质、社会和经济的变化，导致估算增加的情况。此种情况可能发生，也可能不发生。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]