[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-894949":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},894949,581,1,"单选题","下列各项中属于世界银行工程造价构成中项目直接建设成本的是（）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","开工试车费",false,{"key":16,"text":17,"correct":14},"B","生产前费用",{"key":19,"text":20,"correct":14},"C","业主的行政性费用",{"key":22,"text":23,"correct":24},"D","土地征购费",true,"项目直接建设成本包括土地征购费、场外设施费用、场地费用、工艺设备费、设备安装费、管道系统费用、电气设备费、电气安装费、仪器仪表费、机械的绝缘和油漆费、工艺建筑费、服务性建筑费用、工厂普通公共设施费、车辆费和其他当地费用。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]