[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-894946":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},894946,581,1,"单选题","在世界银行规定的项目总建设成本中，未明确项目的准备金的目的是为了（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","支付那些估算时不可能明确的潜在项目",true,{"key":16,"text":17,"correct":18},"B","支付工作范围以外可能增加的项目",false,{"key":20,"text":21,"correct":18},"C","应付天灾、非正常经济情况及罢工等情况",{"key":23,"text":24,"correct":18},"D","用来补偿估算的误差","未明确项目准备金:此项准备金用于在估算时不可能明确的潜在项目，包括那些在做成本估算时因为缺乏完整、准确和详细的资料而不能完全预见和不能注明的项目，并且这些项目是必须完成的,或它们的费甩是必定要发生的。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]