[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-894945":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},894945,581,1,"单选题","已知某世行项目各项数据如下：项目管理费500 万元，开工试车费300 万元，业主的行政性费用100 万元，生产前费用600 万元，运费和保险费150 万元，地方税100 万元，建设成本上升费用120 万元，则该项目间接建设成本为（）万元。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","1000",false,{"key":16,"text":17,"correct":14},"B","1500",{"key":19,"text":20,"correct":21},"C","1750",true,{"key":23,"text":24,"correct":14},"D","1870","项目间接建设成本的组成：1)项目管理费；2)开工试车费。3)业主的行政性费用。4)生产前费用。5)运费和保险费。6)地方税。则该项目间接建设成本=500+300+100+600+150+100=1750 万元。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]