[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-894941":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},894941,581,1,"单选题","根据《建设项目经济评价方法与参数（第三版）》，建设投资由（）三项费用构成。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","工程费用、建设期利息、预备费",false,{"key":16,"text":17,"correct":14},"B","建设费用、建设期利息、流动资金",{"key":19,"text":20,"correct":21},"C","工程费用、工程建设其他费用、预备费",true,{"key":23,"text":24,"correct":14},"D","建筑安装工程费、设备及工器具购置费、工程建设其他费用","建设投资包括:工程费用、工程建设其他费用和预备费三部分。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]