[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-894939":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},894939,581,1,"单选题","下列工程项目计划表中，用来阐明各单位工程的建筑面积、投资额、新增固定资产、新增生产能力等建筑总规模及本年计划完成情况的是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","年度竣工投产交付实用计划表",true,{"key":16,"text":17,"correct":18},"B","年度计划项目表",false,{"key":20,"text":21,"correct":18},"C","年度建设资金平衡表",{"key":23,"text":24,"correct":18},"D","按资计划年度分配表","年度竣工投产交付使用计划表,用来阐明各单位工程的建筑面积、投资额、新增固定资产、新增生产能力等建筑总规模及本年计划完成情况，^并阐明其竣工日期。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]