[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-894934":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},894934,581,1,"单选题","下列进度计划表中，用来明确各种设计文件交付日期，主要设备交货日期，施工单位进场日期，水、电及道路接通日期等的是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","工程项目总进度计划表",false,{"key":16,"text":17,"correct":18},"B","工程项目进度平衡表",true,{"key":20,"text":21,"correct":14},"C","工程项目施工总进度表",{"key":23,"text":24,"correct":14},"D","单位工程总进度计划表","工程项目进度平衡表。用来明确各种设计文件交付日期，主要设备交货日期，施工单位进场日期，水电及道路接通日期等，以保证工程建设中各个环节相互衔接，确保工程项目按期投产或交付使用。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]