[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-894933":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},894933,581,1,"单选题","下列建设工程项目目标控制方法中，可用来综合控制工程进度和工程造价的方法是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","决策树法和流程图法",false,{"key":16,"text":17,"correct":18},"B","S 曲线法和香蕉曲线法",true,{"key":20,"text":21,"correct":14},"C","横道图法和树枝图法",{"key":23,"text":24,"correct":14},"D","网络图法和横道图法","S 曲线可用于控制工程造价和工程进度。香蕉曲线法的原理与S 曲线法的原理基本相同，与S 曲线法相同，香蕉曲线同样可用来控制工程造价和工程进度。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]