[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-894926":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},894926,581,1,"单选题","为了有效地控制建设工程项目目标，可采取的组织措施之一是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","定制工作考核标准",true,{"key":16,"text":17,"correct":18},"B","论证技术方案",false,{"key":20,"text":21,"correct":18},"C","审查工程付款",{"key":23,"text":24,"correct":18},"D","选择合同计价方式","组织措施：控制是由人来执行的，监督按计划要求投入劳动力、机具、设备、材料，巡视、检查工程运行情况，对工程信息的收集、加工、整理、反馈，发现和预测目标偏差，采取纠正行动等都需要事先委任执行人员，授予相应职权，确定职责，制定工作考核标准，并力求使之一体化运行。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]