[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-894925":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},894925,581,1,"单选题","下列方法中，可用来综合控制工程进度和工程造价的是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","香蕉曲线法和S 曲线法",true,{"key":16,"text":17,"correct":18},"B","网络计划法和控制图法",false,{"key":20,"text":21,"correct":18},"C","因果分析图法和排列图法",{"key":23,"text":24,"correct":18},"D","价值工程法和直方图法","香蕉曲线法的原理与S 曲线法的原理基本相同，其主要区别在于：香蕉曲线是以工程网络计划为基础绘制的。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]