[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-894917":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},894917,581,1,"单选题","建设工程采用CM 承包模式时，CM 单位有代理型和非代理型两种。工程分包商的签约对象是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","代理型为业主，非代理型为CM 单位",true,{"key":16,"text":17,"correct":18},"B","代理型为CM 单位，非代理型为业主",false,{"key":20,"text":21,"correct":18},"C","无论代理型或非代理型，均为业主",{"key":23,"text":24,"correct":18},"D","无论代理型或非代理型，均为CM 单位","CM 单位有代理型（Agency）和非代理型（Non—Agency）两种。代理型的CM 单位不负责工程分包的发包，与分包单位的合同由建设单位直接签订。而非代理型的CM 单位直接与分包单位签订分包合同。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]