[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-894914":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},894914,581,1,"单选题","下列项目管理组织机构形式中，未明确项目经理角色的是（）组织机构。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","职能制",false,{"key":16,"text":17,"correct":18},"B","弱矩阵制",true,{"key":20,"text":21,"correct":14},"C","平衡矩阵制",{"key":23,"text":24,"correct":14},"D","强矩阵制","弱矩阵制组织中，并未明确对项目目标负责的项目经理。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]