[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-894888":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},894888,581,1,"单选题","按照工程建设项目发展的内在规律，投资建设一个工程项目都要经过投资决策和建设实施两个发展时期。这两个发展时期又可分为若干个阶段，它们之间()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","次序可以颠倒，但不能交叉",false,{"key":16,"text":17,"correct":18},"B","次序不能颠倒，但可以合理交叉",true,{"key":20,"text":21,"correct":14},"C","次序不能颠倒，也不能交叉",{"key":23,"text":24,"correct":14},"D","次序可以颠倒，也可以交叉","工程项目建设程序。投资建设一个工程项目都要经过投资决策和建设实施两个发展时期。这两个发展时期又可分为若干个阶段，它们之间存在着严格的先后次序，可以进行合理的交叉，但不能任意颠倒次序。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]