[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-894886":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},894886,581,1,"单选题","根据《国务院关于投资体制改革的决定》，企业不使用政府资金投资建设《政府核准的投资项目目录》中的项目时，企业仅需向政府提交()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","项目申请报告",true,{"key":16,"text":17,"correct":18},"B","项目可行性研究报告",false,{"key":20,"text":21,"correct":18},"C","项目开工报告",{"key":23,"text":24,"correct":18},"D","项目初步设计文件","企业投资建设《政府核准的投资项目目录》中的项目时，仅需向政府提交项目申请报告，不再经过批准项目建议书、可行性研究报告和开工报告的程序。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]