[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-894885":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},894885,581,1,"单选题","世界银行贷款项目的建设周期中各工作阶段的正确顺序是()。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","项目选定、项目评估、项目准备、项目谈判、项目实施、项目总结评价",false,{"key":16,"text":17,"correct":14},"B","项目评估、项目选定、项目谈判、项目准备、项目实施、项目总结评价",{"key":19,"text":20,"correct":21},"C","项目选定、项目准备、项目评估、项目谈判、项目实施、项目总结评价",true,{"key":23,"text":24,"correct":14},"D","项目评估、项目选定、项目准备、项目谈判、项目实施、项目总结评价","以世界银行贷款项目为例，其建设周期包括项目选定、项目准备、项目评估、项目谈判、项目实施和项目总结评价六个阶段.世界银行贷款选准评谈实总",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]