[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-894876":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},894876,581,1,"单选题","下列不属于建设单位在建设准备阶段应进行的工作是（）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","择优选定承包单位",false,{"key":16,"text":17,"correct":14},"B","组织招标选择设备、材料供应商",{"key":19,"text":20,"correct":14},"C","完成征地拆迁工作",{"key":22,"text":23,"correct":24},"D","编制项目管理实施规划",true,"建设准备：1)征地、拆迁和场地平整 2)完成施工用水、电、通讯、道路等接通工作 3)组织招标选择工程监理单位、施工单位及设备、材料供应商 4)准备必要的施工图纸",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]