[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-894843":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},894843,581,1,"单选题","某项目中建筑安装工程费用为560 万元，设备工器具购置费为330 万元，工程建设其他费用为133 万元，基本预备费102 万元，涨价预备费55 万元，建设期贷款利息59 万元，则静态投资为（）万元。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","1023",false,{"key":16,"text":17,"correct":18},"B","1125",true,{"key":20,"text":21,"correct":14},"C","1180",{"key":23,"text":24,"correct":14},"D","1239","静态投资包括建筑安装工程费、设备和工器具购置费、工程建设其他费用、基本预备费，以及因工程量误差而引起的工程造价的增减等。因此静态投资=560+330+133+102=1125(万元）",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]