[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-894830":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},894830,581,1,"单选题","建设工程全要素造价管理是指要实现（）的集成管理。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","人工费、材料费、施工机具使用费",false,{"key":16,"text":17,"correct":14},"B","直接成本、间接成本、规费、利润",{"key":19,"text":20,"correct":21},"C","工程成本、工期、质量、安全、环境",true,{"key":23,"text":24,"correct":14},"D","建筑安装工程费用、设备工器具费用、工程建设其他费用","控制建设工程造价不仅仅是要控制建设工程本身的建造成本，还应同时考虑工期成本、质量成本、安全与环境成本的控制，从而实现工程成本、工期、质量、安全、环境的集成管理。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]