[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-894823":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},894823,581,1,"单选题","—个买卖合同执行的是政府定价，2009 年2 月1 日订立合同时价格为每千克100 元，合同规定2009 年4 月1 日交货，违约金为每千克10 元，交货后付款。但卖方直至2009 年6 月1 日才交货，而政府定价于2009 年5 月1 日调整为每千克120 元，买方应当按照每千克（）元的价格向卖方付款。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","90",true,{"key":16,"text":17,"correct":18},"B","100",false,{"key":20,"text":21,"correct":18},"C","110",{"key":23,"text":24,"correct":18},"D","120","A 因为是卖方违约，所以要按照较低的价格执行，同时扣除他的违约金，那就是100-10=90 元。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]