[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-894762":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},894762,580,2,"多选题","在工程建设的施工阶段，工程竣工验收合格后，发、承包人应当办清竣工结算，结算时，先由承包人提交竣工结算书，由（ ）核对。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","发包人",true,{"key":16,"text":17,"correct":18},"B","工程造价管理机构",false,{"key":20,"text":21,"correct":14},"C","业主",{"key":23,"text":24,"correct":18},"D","行业建设主管部门",{"key":26,"text":27,"correct":18},"E","人民法","AC","",{"id":6,"name":31,"category":32,"favorite":33},"[土木建筑工程]建设工程计量与计价实务","建筑工程",0]