[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-894760":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},894760,580,2,"多选题","建设工程项目是指为完成依法立项的（ ）等各类工程而进行的、有起止日期的、达到规定要求的一组相互关联的受控活动组成的特定过程，包括策划、勘察、设计、采购、施工、试运行、竣工验收和考核评价等。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","新建",true,{"key":16,"text":17,"correct":14},"B","扩建",{"key":19,"text":20,"correct":21},"C","迁建",false,{"key":23,"text":24,"correct":14},"D","改建",{"key":26,"text":27,"correct":21},"E","恢复","ABD","建设工程项目是指为完成依法立项的新建、改建、扩建等各类工程而进行的、有起止日期的、达到规定要求的一组相互关联的受控活动组成的特定过程，包括策划、勘察、设计、采购、施工、试运行、竣工验收和考核评价等。",{"id":6,"name":31,"category":32,"favorite":33},"[土木建筑工程]建设工程计量与计价实务","建筑工程",0]