[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-894741":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},894741,580,2,"多选题","根据《建设工程工程量清单计价规范》（GB50500-2013），关于投标文件措施项目计价表的编制，下列说法正确的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","单价措施项目计价表应采用综合单价方式计价",true,{"key":16,"text":17,"correct":18},"B","总价措施项目计价表应包含规费和建筑业增值税",false,{"key":20,"text":21,"correct":14},"C","不能精确计量的措施项目应编制总价措施项目计价表",{"key":23,"text":24,"correct":18},"D","总价措施项目的内容确定与招标人拟定的措施清单无关",{"key":26,"text":27,"correct":18},"E","总价措施项目的内容确定与投标人投标时拟定的施工组织设计无关","AC","本题考查的是投标报价的编制。对于不能精确计量的措施项目，应编制总价措施项目清单与计价表。投标人对措施项目中的总价项目投标报价应遵循以下原则：（1）措施项目的内容应依据招标人提供的措施项目清单和投标人投标时拟定的施工组织设计或施工方案确定。（2）措施项目费由投标人自主确定，但其中安全文明施工费必须按照国家或省级、行业建设主管部门的规定计价，不得作为竞争性费用。招标人不得要求投标人对该项费用进行优惠，投标人也不得将该项费用参与市场竞争。",{"id":6,"name":31,"category":32,"favorite":33},"[土木建筑工程]建设工程计量与计价实务","建筑工程",0]