[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-894739":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},894739,580,2,"多选题","下列费用中，由招标人填写金额，投标人直接计入投标总价的有（ ）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","材料设备暂估价",true,{"key":16,"text":17,"correct":14},"B","专业工程暂估价",{"key":19,"text":20,"correct":14},"C","暂列金额",{"key":22,"text":23,"correct":24},"D","计日工合价",false,{"key":26,"text":27,"correct":24},"E","总承包服务费","ABC","本题考查的是其他项目清单。暂列金额、暂估价（包括材料暂估单价、工程设备暂估单价、专业工程暂估价）相关表格由招标人填写，投标人计入投标总价中；计日工单价由投标人自主报价，暂定数量计入投标总价中；总承包服务费投标时，费率及金额由投标人自主报价，计入投标总价中。",{"id":6,"name":31,"category":32,"favorite":33},"[土木建筑工程]建设工程计量与计价实务","建筑工程",0]