[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-894734":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},894734,580,2,"多选题","根据《房屋建筑与装饰工程工程量计算规范》（GB 50854-2013），回填工程量计算正确的有（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","场地回填，回填面积乘以平均回填厚度",true,{"key":16,"text":17,"correct":14},"B","室内回填，主墙间净面积乘以回填厚度，不扣除间隔墙",{"key":19,"text":20,"correct":21},"C","室内回填，主墙间净面积乘以回填厚度，扣除间隔墙",false,{"key":23,"text":24,"correct":21},"D","基础回填，挖方清单项目工程量减去自然地坪以下埋设的基础体积（不包括基础垫层）",{"key":26,"text":27,"correct":14},"E","基础回填，挖方清单项目工程量减去自然地坪以下埋设的基础体积（包括基础垫层及其他构筑物）","ABE","本题考查的是石方工程、回填。按设计图示尺寸以体积计算。（1）场地回填：回填面积乘以平均回填厚度；（2）室内回填：主墙间净面积乘以回填厚度，不扣除间隔墙；（3）基础回填：挖方清单项目工程量减去自然地坪以下埋设的基础体积（包括基础垫层及其他构筑物）。",{"id":6,"name":31,"category":32,"favorite":33},"[土木建筑工程]建设工程计量与计价实务","建筑工程",0]