[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-894732":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},894732,580,2,"多选题","关于工程量清单及其编制，下列说法中正确的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","招标工程量清单必须作为投标文件的组成部分",false,{"key":16,"text":17,"correct":18},"B","安全文明施工费应列入以“项”为单位计价的措施项目清单中",true,{"key":20,"text":21,"correct":14},"C","招标工程量清单的准确性和完整性由其编制人负责",{"key":23,"text":24,"correct":14},"D","暂列金额中包括用于施工中必然发生但暂不能确定价格的材料、设备的费用",{"key":26,"text":27,"correct":18},"E","计价规范中未列的规费项目，应根据省级政府或省级有关权力部门的规定列项","BE","本题考查的是土建工程工程量清单的编制方法。选项A错误，招标工程量清单必须作为招标文件的组成部分；选项C错误，招标工程量清单的准确性和完整性由其招标人负责；选项D错误，暂估价中包括用于施工中必然发生但暂不能确定价格的材料、设备的费用",{"id":6,"name":31,"category":32,"favorite":33},"[土木建筑工程]建设工程计量与计价实务","建筑工程",0]