[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-894731":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},894731,580,2,"多选题","关于措施项目工程量清单编制与计价，下列说法中正确的是（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","不能计算工程量的措施项目也可以采用分部分项工程量清单方式编制",false,{"key":16,"text":17,"correct":18},"B","安全文明施工费按总价方式编制，其计算基础可为“定额基价”、“定额人工费”",true,{"key":20,"text":21,"correct":14},"C","总价措施项目清单表应列明计量单位、费率、金额等内容",{"key":23,"text":24,"correct":18},"D","除安全文明施工费外的其他总价措施项目的计算基础可为“定额人工费”",{"key":26,"text":27,"correct":18},"E","按施工方案计算的总价措施项目可以只需填“金额”数值","BDE","本题考查的是土建工程工程量清单的编制方法。只有可以计算工程量的项目才可以按照分部分项工程量清单编制。安全文明施工费也可以定额人工费为基数。总价措施费中没有计量单位。",{"id":6,"name":31,"category":32,"favorite":33},"[土木建筑工程]建设工程计量与计价实务","建筑工程",0]