[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-894729":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},894729,580,2,"多选题","根据《建设工程工程量清单计价规范》（GB-50500-2013），关于分部分项工程量清单的编制，下列说法正确的有（）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","以重量计算的项目，其计量单位应为吨或千克",true,{"key":16,"text":17,"correct":14},"B","以吨为计量单位时，其计算结果应保留三位小数",{"key":19,"text":20,"correct":21},"C","以立方米为计量单位时，其计算结果应保留三位小数",false,{"key":23,"text":24,"correct":21},"D","以千克为计量单位时，其计算结果应保留一位小数",{"key":26,"text":27,"correct":14},"E","以“个”、“项”为单位的，应取整数","ABE","C选项，以立方米为计量单位时，其计算结果应保留二位小数。D选项，以千克为计量单位时，其计算结果应保留二位小数。因此，正确选项为 ABE。",{"id":6,"name":31,"category":32,"favorite":33},"[土木建筑工程]建设工程计量与计价实务","建筑工程",0]