[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-894720":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},894720,580,2,"多选题","根据《建设工程工程量清单计价规范》（GB 50500－2013），建筑工程工程量按长度计算的项目有（ ）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","砖砌地垄墙",true,{"key":16,"text":17,"correct":14},"B","石栏杆",{"key":19,"text":20,"correct":14},"C","石地沟、明沟",{"key":22,"text":23,"correct":24},"D","现浇混凝土天沟",false,{"key":26,"text":27,"correct":14},"E","现浇混凝土地沟","ABCE","本题考查的是混凝土及钢筋混凝土工程。零星砌砖，小便槽、地垄墙可按长度计算；混凝土天沟（檐沟）、挑檐板工程量按设计图示尺寸以体积计算。",{"id":6,"name":31,"category":32,"favorite":33},"[土木建筑工程]建设工程计量与计价实务","建筑工程",0]