[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-894719":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},894719,580,2,"多选题","根据《建设工程工程量清单计价规范》（GB 50500－2013），现浇混凝土工程量计算正确的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","构造柱工程量包括嵌入墙体部分",true,{"key":16,"text":17,"correct":18},"B","梁工程量不包括伸入墙内的梁头体积",false,{"key":20,"text":21,"correct":14},"C","墙体工程量包括墙垛体积",{"key":23,"text":24,"correct":14},"D","有梁板按梁、板体积之和计算工程量",{"key":26,"text":27,"correct":14},"E","无梁板伸入墙内的板头和柱帽并入板体积内计算","ACDE","本题考查的是混凝土及钢筋混凝土工程。现浇混凝土梁，工程量按设计图示尺寸以体积计算。扣除构件内钢筋、预埋铁件所占体积，伸入墙内的梁头、梁垫并入梁体积内",{"id":6,"name":31,"category":32,"favorite":33},"[土木建筑工程]建设工程计量与计价实务","建筑工程",0]