[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-894716":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},894716,580,2,"多选题","下列费用中,由招标人填写金额,投标人直接计入投标总价的有（）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","材料设备暂估价",false,{"key":16,"text":17,"correct":18},"B","专业工程暂估价",true,{"key":20,"text":21,"correct":18},"C","暂列金额",{"key":23,"text":24,"correct":14},"D","计日工单价",{"key":26,"text":27,"correct":14},"E","总承包服务费","BC","本题考查的是其他项目清单。“专业工程暂估价、暂列金额”由招标人填写金额，投标人直接计入投标总价。因此，正确选项为 BC。",{"id":6,"name":31,"category":32,"favorite":33},"[土木建筑工程]建设工程计量与计价实务","建筑工程",0]