[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-894714":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},894714,580,2,"多选题","根据《房屋建筑与装饰工程工程量计算规范》（GB50854-2013）规定，以下关于措施项目工程量计算，说法正确的有（）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","垂直运输费用，按施工工期日历天数计算",true,{"key":16,"text":17,"correct":14},"B","大型机械设备进出场及安拆，按使用数量计算",{"key":19,"text":20,"correct":21},"C","施工降水按降水深度来计算",false,{"key":23,"text":24,"correct":21},"D","超高施工增加，按建筑物总建筑面积计算",{"key":26,"text":27,"correct":21},"E","同一建筑物有不同檐高时，以最低檐高的建筑面积计算超高施工增加","AB","垂直运输可按建筑面积计算也可以按施工工期日历天数计算，以天为单位。大型机械设备进出场及安拆工程量按使用机械设备的数量“台次”计算。排水、降水按排水、降水日历天数“昼夜”计算。超高施工增加按建筑物超高部分的建筑面积计算。同一建筑物有不同檐高时，可按不同高度的建筑面积分别计算建筑面积。",{"id":6,"name":31,"category":32,"favorite":33},"[土木建筑工程]建设工程计量与计价实务","建筑工程",0]