[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-894712":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},894712,580,2,"多选题","根据《房屋建筑与装饰工程工程量计算规范》（GB\u002FT50854-2013），打桩工程量计算正确的是（）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","打预制钢筋混凝土方桩，按设计图示尺寸桩长以米计算，送桩工程量另计",false,{"key":16,"text":17,"correct":18},"B","打预制钢筋混凝土管桩，按设计图示数量以根计算、截桩头工程量另计",true,{"key":20,"text":21,"correct":14},"C","钢管桩按设计图示截面积乘以桩长、以实体积计算",{"key":23,"text":24,"correct":14},"D","钢板桩按不同板幅以设计长度计算",{"key":26,"text":27,"correct":18},"E","预制钢筋混凝土管桩试验桩应在工程量清单中单独列项","BE","预制钢筋混凝土方桩、预制钢筋混凝土管桩以米计量，按设计图示尺寸以桩长（包括桩尖）计算；或以立方米计量，按设计图示截面积乘以桩长（包括桩尖）以实体积计算；或以根计量，按设计图示数量计算。钢管桩以吨计量，按设计图示尺寸以质量计算；以根计量，按设计图示数量计算。钢板桩以吨计量，按设计图示尺寸以质量计算；以平方米计量，按设计图示墙中心线长乘以桩长以面积计算。",{"id":6,"name":31,"category":32,"favorite":33},"[土木建筑工程]建设工程计量与计价实务","建筑工程",0]