[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-894711":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},894711,580,2,"多选题","根据《房屋建筑与装饰工程工程量计算规范》（GB50854-2013），关于土方工程量计算与项目列项，说法正确的有（）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","建筑物场地挖、填厚度≤±300mm的挖土应按一般土方项目编码列项",false,{"key":16,"text":17,"correct":18},"B","平整场地工程量按设计图示尺寸以建筑物首层建筑面积计算",true,{"key":20,"text":21,"correct":18},"C","挖一般土方应按设计图示尺寸以挖掘前天然密实体积计算",{"key":23,"text":24,"correct":14},"D","挖沟槽土方工程量按沟槽设计图示中心线长度计算",{"key":26,"text":27,"correct":18},"E","挖基坑土方工程量按设计图示尺寸以体积计算","BCE","建筑物场地挖、填厚度≤±300mm的挖土应按平整场地项目编码列项。挖沟槽土方工程量应按计图示尺寸以基础垫层底面积乘以挖土深度计算。",{"id":6,"name":31,"category":32,"favorite":33},"[土木建筑工程]建设工程计量与计价实务","建筑工程",0]